The _____ is the product of the percent complete and the sum of the estimated costs of all the specific activities that make up a work package or the project.
Answers
Answer 1
The answer is the total budget cost. It is the one
responsible of the expense that the company needs and the estimated expense
that they had used that may be of use as their basis and for the their
futureĀ period.